On most purchase orders, the monthly progress report says one thing and the shop floor says another. The gap between the two is where delivery dates are lost.
Where the gap comes from
A percentage in a progress report is not a measurement. It is an estimate, made by the party with the strongest interest in showing the order on track. That does not make suppliers dishonest: it makes their reports optimistic by design.
- Progress is measured on effort and plan, not on the physical state of the equipment.
- Milestone payments create pressure to report milestones as reached.
- Sub-suppliers and raw materials are often invisible in the main supplier's report.
- Engineering documents still waiting for approval hold back fabrication, even when the report says otherwise.
- Rework after inspections and non-conformities rarely shows up as lost progress.
Warning signs
Some patterns should always prompt a closer look:
- Progress jumps just before a payment milestone.
- Percentages stay flat for weeks and then leap forward.
- Reports without evidence: no dated photos, no documents, no names.
- Fabrication reported as well advanced while key drawings or the ITP are not yet approved.
- Vague answers on when raw materials and bought-out items will arrive.
- A workshop visibly loaded with other customers' work.
How to verify progress
Verification does not mean distrust. It means agreeing from the start how progress will be demonstrated.
- Agree a weighted progress breakdown at kick-off: engineering, procurement, fabrication, testing, shipping.
- Ask for evidence with every update: dated photos, sub-order confirmations, material certificates, route cards.
- Cross-check reported progress with the status of vendor documents (VDRL).
- Plan shop visits at the moments that matter, not only before the FAT.
- Follow the trend over several reports, not a single snapshot.
- Compare what is late with the project's critical path.
From gap to action
Finding a gap is only useful if it leads to a decision. When reported and real progress diverge, the next step is a recovery plan with clear actions, owners and dates, agreed with the supplier and escalated to its management when needed. Expediting priorities can then be moved to where the risk is highest.
The earlier the gap is found, the more options remain: parallel work, split shipments, alternative sources. Found late, it becomes a delay that can only be reported.
“Good expediting doesn't simply report delays. It prevents surprises and drives decisions.”
Roberto Reino